Work is Underway
10/27/2024 11:05:46 AM
Susan Kuning
Author | |
Date Added |
The contractor has installed all the infrastructure(cabling) for all the ceiling speakers, including the ones for the future (hall, lobby, etc.) The team was able to mount the new main speakers as well. Next week, they'll install all the rack equipment, the ceiling speakers in the library section of the sanctuary, and officially cut over to the new main speakers while removing the old ones. Tuning of the new main speakers will take place mid-Wednesday morning and their plan is to be wrapped up by the end of that day.
Tue, September 16 2025
23 Elul 5785
Register for Adult Ed Classes
Click here to see the full list of classes and to sign up!
Register for the 2025-2026 School Year Now!
Join Our Mailing List
Privacy Settings | Privacy Policy | Member Terms
©2025 All rights reserved. Find out more about ShulCloud